The City of El Paso is continuing to grow. To maintain this growth, construction is a necessary evil for people in the city. Find out what Eastside streets will have construction this week.

Border West Expressway Project

Paisano Drive (US 85)
Friday, Jan. 13, to Monday, Jan. 16
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from San Francisco to Spur 1966

Closure is to switch traffic.
Friday, Jan. 20, to Monday, Jan. 23
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from San Francisco to Spur 1966

Closure is to demo a bridge.
Monday, Jan. 23, to Friday, Jan. 27
9 p.m. to 5 a.m. (nightly full closure)

  • Westbound and eastbound from San Francisco to Spur 1966

Closure is to demo a bridge.
Friday, Feb. 3, to Sunday, Feb. 5
9 a.m. to 10 p.m. (continuous closure)

  • Left lane on westbound from Corona Avenue to US 54

Closure is to stage beams.
Friday, Feb. 3, to Monday, Feb. 6

9 p.m. to 5 a.m. (continuous full closure)

  • Eastbound and westbound from Saint Vrain Street to San Marcial Street

Closure is to place beams.

Delta
Wednesday, Jan. 25, to Thursday, Jan. 26
9 a.m. to 7 p.m. (continuous closure)

  • The right lane westbound from San Marcial Street to Cypress Avenue

Closure is to stage beams.
Thursday, Jan. 26, to Friday, Jan. 27
7 p.m. to 5 a.m. (continuous full closure)

  • Eastbound and westbound from San Marcial Street to Coles Street

Closure is to place beams.

Doniphan Drive
Friday, Jan. 13, to Monday, Jan. 16
(continuous full closure)

  • Eastbound right lane from Racetrack Drive to Race Track Drive

This closure is needed to stage beams.

Loop 375
Tuesday, Jan. 24
9 p.m. to 5 a.m. (nightly full closure)

  • Westbound from US 54 to Park Street

This closure is to install an overhead-sign board structure.

Joe Battle (Loop 375) Widening Project
Monday through Friday
7 a.m. to 4 p.m. (at different times throughout the day and at different locations)

  • Alternate north and southbound entrance and exit ramp closures along Joe Battle (Loop 375) between the Bob Hope overpass and the Montana overpass
  • Alternate north and southbound right and left lane closures along Joe Battle Boulevard between the Montana overpass and the Bob Hope overpass
  • Alternate north and southbound turnaround closures along Joe Battle Boulevard between the Bob Hope overpass and the Montana overpass

Monday through Friday
9 a.m. to 4 p.m. (at different times throughout the day and at different locations)

  • North and southbound right lane closure on Joe Battle (Loop 375) between the Bob Hope overpass and the Montana overpass

These closures are necessary for guardrail and electrical work.

I-10 Americas Phase IV Project

Saturday, Jan. 14, and Sunday, Jan. 15
6 a.m. to 8 p.m.

  • I-10 westbound between the Don Haskins exit ramp and Zaragoza overpass

Crews will be working on concrete pavements.
Monday, Jan. 16, through Wednesday, Jan. 18
8 a.m. to 4 p.m.

  • I-10 eastbound between the Zaragoza exit ramp and Eastlake entrance ramp

Crews will be installing barriers.

Find out more details on the planned road closures and construction around El Paso on the Texas Department of Transportation Website.